Paya Lebar Quarter Office
Corporate office, 8,400 sq ft fit-out
Location
Paya Lebar Quarter
Size
8,400 sq ft
Duration
10 weeks
Year
2025
A regional fintech team's first Singapore office, fitted out around a hard deadline: staff moving in the week after their old lease expired.
The brief
A shell-and-core floor with a fixed move-in date and a headcount that would grow 40% within the year. The design had to work on day one and still make sense after the team scaled up.
Our approach
We phased procurement so long-lead items — glazing, joinery — were ordered before the design was fully signed off, running design development and fabrication in parallel rather than in sequence. Desking was laid out in modular pods that could absorb headcount growth without a second fit-out.
The result
Handover landed four days ahead of the lease deadline. The client's facilities lead has since reordered the same desking pods twice without needing us back on site.